Error: ‘linkDate cannot be null’ when processing RCPC

In this article, we explain why the ‘linkDate cannot be null’ error appears when postponing an RCPC in Mosaic.

Y
Written by Yusef Abulaynain
Updated over 5 months ago

Mosaic requires a decision date when you complete a Review Child Protection Conference (RCPC). However, if you defer, you will need to record the date of this decision, and this should be entered in the ‘Actual Date of Conference’ field.

Please note that you can see this field in the CLC configuration of the form, and it's part of the form that shouldn't be amended locally, as this can cause errors. If you can't view or complete this field, it may be due to a variation from the CLC configuration, which should be reverted.